Project Details
- Supply and placement of 13,000 Tonnes of filter and armour
granite rock
- Demolition and removal of 3,300 Tonnes of existing
limestone seawall
- Screw Piling Pile sleeves & installation of access stairs to the
beach
- Extensive dewatering via spearing set up to work below AHD
levels
- Use of GPS for placement of rock and batter preparation
- Traffic and Pedestrian Management
- Storm and inclement weather management working on the
coast
|
|
Key Information
Contract Period:
3 Months
Client:
City of Rockingham
Contract Value:
$2.0m
|
|