Mersey Point Seawall Stage 2
Recent Projects
Mersey Point Granite Seawall Stage 2
The Construction of a 280m granite seawall in Rockingham WA for the City of Rockingham
Project Details
  • Supply and placement of 13,000 Tonnes of filter and armour granite rock
  • Demolition and removal of 3,300 Tonnes of existing limestone seawall
  • Screw Piling Pile sleeves & installation of access stairs to the beach
  • Extensive dewatering via spearing set up to work below AHD levels
  • Use of GPS for placement of rock and batter preparation
  • Traffic and Pedestrian Management
  • Storm and inclement weather management working on the coast
Key Information

Contract Period:
3 Months

Client:
City of Rockingham

Contract Value:
$2.0m
Home
About Us
Capabilities
Projects
Plant Hire
Media
Contact Us